I am happy to inform you that we have a confirmed timeline for construction for the Columbarium and Memorial Garden.

Underground utility work has been completed and construction drawings will be finalized by the beginning of January. If all goes according to plan, the contractor will submit the drawings for permits enabling construction to begin by January 30. Construction time is estimated as 6-8 weeks. The plan is for the project to be completed by Easter.

Once we have a firm completion date, we will plan a dedication and inurnments for those of you who have cremains of loved ones waiting for the garden.

We appreciate your patience and assure you that we are doing everything possible to expedite the construction of the project while we tend to the many details that will make it a safe, attractive and spiritual place of eternal rest.

If you have any concerns, please don’t hesitate to contact me.

Sincerely,
Very Rev. Robert J. Kus
Pastor